Writing to alderman and newspaper gets results

Every time I commute to work from the Ravenswood Metra station, I get annoyed. Metra has yet to finish the inbound platform after almost 10 years of delays. So I emailed the alderman to ask why, and CC:d Block Club Chicago, the local news outlet. Reporter Alex Hernandez called me the next morning, and ran this story today:

The Ravenswood Metra station overhaul that began more than a decade ago is hitting yet another bump. 

The $30 million project to renovate 11 bridges along Metra’s Union Pacific North line was announced in 2010. Construction of the western side of the Ravenswood station, 4800 N. Ravenswood Ave., was completed in 2015 — but the rest of the project is ongoing.

Previous delays to the project were caused in part by a polar vortex in 2014 and cuts in funding to Metra in 2010. The work was fully funded in 2020, and officials planned to begin the final phase of the eastern portion of the station in the spring.

But now it’s supply chain issues that are delaying work, Metra spokesperson Meg Reile said. 

“It’s still up in the air because of supply chain issues,” Reile said. “That’s what’s holding up the end of this project.” 

Reile did not provide specifics about what items crews are waiting for, but she said the goal is to complete the eastern side of the Ravenswood station by the end of the year.

Good to know. My conversations with Hernandez Wednesday and yesterday were enlightening to both of us. And today, I actually saw someone in a hard hat and vest working on the platform, though I have no idea what he was doing.

Will the platform open by year's end? Will the Cubs lose 95 games this season? Will any former presidents get indicted this fall? No one can yet know the answer to any of those questions.