The Daily Parker

Politics, Weather, Photography, and the Dog

Meanwhile, in my neighborhood

The Chicago Transit Authority will demolish my local El station starting May 16th, kicking off a 4-year, $2.1 bn project to rebuild the Red and Purple Lines from Lawrence to Bryn Mawr. Good thing we have an alternative only 400 meters away:

Crews will begin the demolition work on the project’s northern end at Ardmore Avenue and work south, CTA spokeswoman Tammy Chase said. The construction zone spans from Ardmore Avenue to Leland Avenue.

The Lawrence, Argyle, Berwyn and Bryn Mawr stations will close May 16. Temporary stations at Argyle and Bryn Mawr will open that day, according to the CTA.

Crews will also demolish the northbound Red and Purple line tracks between Lawrence and Bryn Mawr. That will include the demolition of 1.5 miles of embankment wall and 11 bridges that span east-west streets in Uptown and Edgewater.

Demolition and the rebuilding of the eastern portion of the tracks is scheduled to wrap up in late 2022, according to the CTA.

From there, work on the western portion of the tracks will commence. This second stage of work will include the construction of the four new stations, which are slated to be opened in 2024.

It's so nice, now that Bruce Rauner has left Springfield, that public works projects can resume. It even looks like we'll have a new Chicago-bound train station at Ravenswood before too long.

Comments are closed